Case Studies - Maintenance

< View all Maintenance Case Studies

Monday, 28th October 2013

Walton On Trent C of E Primary School

Client: Derbyshire County Council

Project Coordinator: Robert Turner BSc(Hon) MBEng

Project duration: 8 weeks

Project value: £143,000

Project Type: Modular Classroom

Contracts Manager: Pat Richmond

Site Manager: Andy Doran

The Gelder Group were entrusted with extending the classroom/teaching space for Walton on Trent C of E Primary School.

The increased level of pupils required the classroom to be completed at the earliest possible date.

The time limits and value for money requirements confirmed that the provision of the demountable building was the most suitable option.

The project included the provision of groundworks, foundations and all water, electrical and mechanical services.

The building is a bespoke design double classroom modular building for Derbyshire County Council.

Health & Safety was a crucial issue thoroughly delivered by Andy Doran on site.

The scheme included the carefully designed access for the disabled.

Robert Turner commented:

'I would like to thank the Team that undertook direct control/management of the project. I was impressed with the professional way they delivered the contract and have found my dealings with The Gelder Group to be extremely positive. Thanks again for a great project delivery'.

Carolyn White, Headteacher, commented:

'The Company was outstanding in every way'.