Monday, 22nd August 2011
St Augustines & Stikney
Client: Lincoln County Council Children Services / Mouchel Property Services
Contract Value: £105K
Duration: 8 Weeks
To take from Gelder Storage and relocate in Stickney primary school grounds, refurbish and redesign to the clients requirements
The new mobile is to provide a much needed Playgroup Kids Club. As part of the refurbishment a canopy and soft pour was installed along with new fencing. The internal of the building was completely stripped out, new insulation and wall boards were fitted along with a complete rewire and fire alarm system to bring the building up to current regulations. A complete new kitchen was fitted along with a Disabled W.C and two new children’s toilet cubicles. The building was inspected by Ofsted and passed with flying colours prior to the building been open and able to accept children.