Monday, 9th May 2011
Lincolnshire County Council
Value: £5,975.00
Drying time: 5 -7 Days
Traditional drying: 5-6 weeks
Property type: Primary School
Navenby School was flooded over the Christmas holiday period and received substantial water damage due to burst pipes in the roof void area. Xeric Systems Technical Director recommended that plaster and plaster board ceilings, vinyl and timber floor areas were strip out to enable the drying.
The areas affected within the school were dried using our speed drying system in 7 days so enabling the school to open on time in the new term.