Case Studies - Retail

< View all Retail Case Studies

Tuesday, 10th July 2012

New Convenience Store, Witham St Hughs, Swinderby

 

Client: Lincolnshire Co-operative Society

Type of Contract: Traditional

Project Duration: 18 Weeks

Value: £340,000

Status: Completed

The project involved the construction of the shell of a new store within tight time restraints for fitting out by the Client.

The works were successfully completed in time to ensure the fit out contractors to carry out their works. 

The store was opened at the intended time.

Project Team

Contracts Manager - Matt Hodgkins
Site Manager - Ian Elsey
Project Surveyor - Stewart Loughton
Buyer - Tom Senescall