< View all Education Case Studies
Monday, 25th June 2012
New Primary School, Scunthorpe St Peter & St Paul C of E Primary School
Client: North Lincs Council
Type of Contract: Traditional
Project Duration: 40 Weeks
Value: £3,000,000
Status: On Site
This building project entailed tree felling and earth moving to form new levels, Precast concrete piling, reinforced concrete foundations with a blockwork superstructure and steel frame to hall and central areas with the roof consisting of timber supporting joists and steel beams supporting a composite roof.
Accommodation consisted of 8no classrooms, a main hall, offices, toilets etc. as well as a fully operational kitchen and servery. Externally affords Staff and Visitor parking, Environmental Teaching Gardens, Playgrounds and a Playing Field.
The project is situated adjacent to a large housing development still under construction, so coordination with the housing consortium with respect of access, services and all associated infrastructure works was of utmost importance.
Project Team
Contracts Manager - Gavin Parker
Site Manager - Cliff Meyer
Project Surveyor - Robert Porter
Buyer - Noel Pepper