Surestart New Childrens Centre, Lincoln

Client: NCH Northern

Architect: K Saint Associates
 
Quantity Surveyor: Capita Symonds Ltd
 
Type of Contract: Traditional
 
M&E Engineers: M J Broome
 
Project Duration: April 2005 - December 2005
 
A new single storey building of traditional construction, including reception area, meeting rooms, children’s play areas, offices, toilets & external play areas.
 
The project was completed two weeks ahead of the contract completion date. This was due to close liaison with the client, design team & ourselves at the early stages of the project, which led to very few technical problems as the project progressed.  
 
Project Team
Contracts Manager - Kevin Manterfield
Site Manager - Shaun Cass
Quantity Surveyor - Iain Cameron