Wednesday, 3rd February 2010

New Drama Block & Dining Room Extension, William Farr School, Welton

Client: Lincolnshire County Council

Consultant: Mouchel Business Services
 
Value: £2,000,000
 
Type of Contract: Cost Plus
 
Project Duration:  52 Weeks
 
Completion Date:  2006
 
The new drama block consists of a steel framed structure on reinforced concrete pad foundations.  Internal walls are load bearing masonry with the external facbric of the building being constructed using polished block work, larch building and Sto render, incorporating curtain walling with a lightweight composite roof. This project was a phased scheme. 
 
The building consists of a drama studio, social space, toilet areas, music practise rooms, lift to the 1st floor areas, plant room music recital room and seven general classrooms.
 
Works were carried out within operation facilities, therefore careful planning and liaison with the client was necessary in order to minimise disruption and ensure the highest 
standards of safety.
 
"Our satisfaction with Gelders has been such that our Governors have always recommended that they be listed as preferred bidders. A team dedicated to the welfare and benefit of our pupils, students and staff. We do not see them as ‘contractors’. We see them as friends"
Paul Strong, Head Teacher