Case Studies - Education

< View all Education Case Studies

Wednesday, 3rd February 2010

New CDT Building, Science Block Extension, Banovallum School, Horncastle

Client: Lincolnshire County Council

Consultant: Mouchel Business Services
 
Value: £2,500,000
 
Type of Contract: Traditional
 
Project Duration:  60 Weeks
 
Completion Date:  November 2008
 
The works included a single storey extension & remodeling to the existing science block, the erection of a new two storey CDT, Arts & music building, remodelling of the existing two storey classroom block & improvements to the existing dining room & music area.  This was a phased scheme. 
 
Gelder Group employees worked closely with the school on a daily basis to ensure that the day to day running of the school was not affected by the building works. The Gelder Group will be returning to the school to carry out improvement works in April this year as part of our framework agreement with Lincolnshire County Council.
 
Works were carried out within operation facilities, therefore careful planning and liaison with the client was necessary in order to minimise disruption and ensure the highest standards of safety.
 
"The Gelder Group gave us total co-operation and minimal disruption, the new CDT building has certainly got the ‘wow’ factor. We will miss them"
Ian Carrol, Head Teacher
 
Project Team
Contracts Manager - Kevin Manterfield
Site Manager - Pete Hooker
Project Surveyor - John Traves