Thursday, 9th February 2012
New Motor Vehicle Workshop St George's Academy, Sleaford
Client: St George’s Academy, Sleaford
Type of Contract: Design & Build
Project Duration: 13 Weeks
Value: £149,000
Status: Completed
The works consisted of a new extension to the motor vehicle workshop which included the erection of a steel frame clad with masonry, aluminium windows, roller shutter doors and an internal two storey office / store. We also provided mechanical vehicular lifting equipment and an exhaust extraction unit.
Works were carried out whilst the school was operational, therefore careful planning and client liaison were essential to ensure high health and safety standards were maintained and minimal disruption to the school occurred.
“The project was an addition to an architecturally sensitive part of the school and the design work was particularly impressive. The finished building looks fantastic and has received nothing but praise from our students, staff and parents. The work was finished to a high quality,on time within a tight deadline and to the agreed budget. We received additional help in kitting the building out, which reflected the outstanding service we received.”
Paul Watson, Principal
Project Team
Design & Build Manager - Matthew Salton
Site Manager - Simon Hope
Project Surveyor - Stewart Loughton
Lead Designer - Jon Cook
Buyer - Noel Pepper