New Kitchen & Dining Facilities at Bassetlaw District Hospital, Worksop
Work to the main high level roof is now ongoing with the main platform roof being watertight. Internally the mechanical and electrical 1st fix works are progressing well with plastering works to follow shortly. The new glazed wall (pictured below) is now being installed with the link walkway to be erected during November / December 2008.
![]() |