On the 28th November 2008 the final phase of the building works carried out at Banovallum School Horncastle was handed over. This phase involved the internal and external refurbishment of the existing 2 storey block, this included overcladding, replacement windows and internal upgrade.

 

Other phases previously completed include a new C.D.T building, extensions to the science laboratories and refurbishment to the dining and music areas.

 

Pictured are left to right (back row): Rob Belton, Rob Meyer, Nick Greenwood, David Gill of Mouchel Group with (front) Ian Carrol Head Teacher shaking hands with Gelder Site Manager Pete Hooker.

 